Bluffs House
A 1960s home, fully off gas
A two-storey brick house from the 1960s, a short walk from the lake, with a gas furnace three times bigger than it needed. We sized a heat pump on the home's own meter data, moved every load to electricity, kept the 200 A service, and had the gas disconnected.
Plan My Electrification →Prefer to talk? Call (416) 670-4030Fixed quote within 1 to 2 business days, sized on your own data.

Bluffs House, Toronto



Every load, one at a time
The house went electric in stages over a few years. Tap between the house as found and today.
The furnace was three times too big
Most heat pumps fail on sizing, not on cold. We compared the old furnace, the energy audit and a year of the home's own meter data before choosing anything.
What happens when it gets cold
Slide the outdoor temperature and watch who carries the house.
Pick an outdoor temperature
Modelled from a year of the home's meter data and the manufacturer's published capacity. Over a full season the duct heater supplies about 1% of the heat.
Six systems, no combustion
Heat pump2 ton inverter heat pump on a wall bracket
- What went in
- A modulating outdoor unit with an air handler in the old furnace's spot, on the existing ducts, installed with Critical Heating and Cooling.
- Why it matters
- It runs long and low instead of blasting on and off, so the house holds a steady temperature.
Backup heat8 kW duct heater, staged and locked out
- What went in
- Set to stage in steps rather than dump all 8 kW at once, and locked out above -15 °C.
- Why it matters
- The settings left at factory default would cost real money every winter.
Hot waterHeat pump water heater, 50 gallon
- What went in
- A hybrid tank that heats water with a small heat pump and dehumidifies the basement as a bonus.
- Why it matters
- Water heating is the second-biggest gas load. Now it is the cheapest electric one.
Fresh airEnergy recovery ventilator
- What went in
- Balanced fresh air, interlocked with the air handler so it moves through the whole house.
- Why it matters
- No combustion indoors and a tighter house both need planned fresh air.
Steam showerElectric steam shower and heated towel bar
- What went in
- An electric steam generator behind the tile, a digital control in the shower and a hard-wired heated towel bar.
- Why it matters
- Comfort loads like this are why the service was checked on real meter data, not a guess. The measured peak already includes it.
Service and panel200 A smart panel, no upgrade
- What went in
- Every electric load, the duct heater, the addition and future battery charging counted by the Code method.
- Why it matters
- A full switch off gas did not need a bigger service.
Concept renderingInduction, electric ovens and its own heat pump
A rear kitchen addition is under way. It gets its own mini split, electric radiant floor and fresh air, so it does not lean on the central system. Its load is already counted in the 141 A.
Fully electric on 200 A
Counted by the Ontario Electrical Safety Code method on 15-minute meter data, with every new load added in.
Where a 1960s house loses its heat
The heat pump is sized for the house as it is today. Three envelope upgrades make it even easier on it.
- Insulate the bare basement wall. The biggest single loss in most 1960s homes.
- Replace the original windows. Double-glazed with no low-E coating, so a quarter of the heat leaves through the glass.
- Air seal. Taking the house from about 4.2 to 3.0 air changes at test pressure.
- Together: the heat pump carries the house unaided down to about -19 °C, and the duct heater runs 60% fewer hours.
The bill, step by step
Annual electricity cost for the fully electric house, modelled on its own meter data.
The order that works
- Start with the data. A year of utility meter data shows the real heating load and what the service can carry.
- Do the easy swaps early. Hot water and cooking can go electric any time, often when the old unit fails.
- Size the heat pump to the house, not the furnace. Oversizing costs comfort and money.
- Set up the backup heat. Staged, locked out above about -15 °C, never left at factory default.
- Add fresh air. An ERV interlocked with the air handler, once combustion is gone.
- Check the service by the Code method. Most homes on 200 A do not need an upgrade.
- Disconnect the gas. Close the account and have the service removed.
- Then battery and solar. Cheap overnight power, backup in an outage, and a lower bill.
How an electrification comes together
- 1Data review. A year of the home's meter data, plus any energy audit, to find the real load.
- 2Sizing and load assessment. Heat pump, backup heat and the service checked together.
- 3Circuits and panel. Existing circuits reused where they fit, breakers matched to the new equipment.
- 4Install, turnkey. Heat pump, air handler and ventilation in one visit with Critical Heating and Cooling, our HVAC partner, under one Energable contract.
- 5Commissioning. Staging, lockouts and thermostat set for this house, not left at default.
- 6Gas off, battery next. Disconnect the gas, then plan backup power and solar on the same data.
Every home ends up here
Going fully electric starts with your own data
Send the address. We review your hourly data, size the heat pump and check your service, then send a fixed quote within 1 to 2 business days.
Go Full Electric →Home Electrification Questions
The kind we would give before you commit a dollar of capital. Tap a question.
Can a 1960s house heat with a heat pump in Toronto winters?
Do I need a 200 A or 400 A service to go fully electric?
How do you size a heat pump for an older home?
What backup heat does a cold-climate heat pump need?
What does going off gas involve?